The level of repairs will be determined by the condition of the equipment.
JSC TGC-11 announced the allocation of additional funding for “measures to improve the reliability of equipment operation.” The company announces an amount of 2.2 billion rubles for its projects planned for the period from 2024 to 2028.
This year, of this amount, TGC-11 plans to spend 876 million rubles. First of all, repairs will be carried out on 22 boiler units at all operating thermal power plants in the city (CHP-3, CHPP-4 and CHPP-5).
The company also notes that salaries of station employees will be increased in order to retain staff.
Let us note that earlier regional prosecutor Alexey Afanasyev explained the scandal that broke out in winter with the failure of power plants by saying that “a large company saved on repairs.” Law enforcement agencies are still investigating this situation.
Let us recall that in December 2023, during severe frosts, the operation of power plants was stopped several times, in particular, CHPP-3 and CHPP-5. TGC-11 then stubbornly denied any information about the accidents, despite official comments from officials and law enforcement agencies.